Kemper Plant

The Kemper County Lignite Plant is a cancer in Mississippi's economy. Bigger Pie has done an extensive body of work regarding the Kemper Plant through the years. From the beginning, the plant's additional capacity was not needed. For years, the building of this plant soared over budget and time constraints ending up costing over $7 billion and 7 years to construct a plant which ultimately did not work.

Featured Work

Southern CEO Dream

Southern Company's Dream

by BPF Published March 4, 2020 The Southern Company’s dream of a multi-billion plant to transform lignite into electricity will be history in four short years. According to a filing with the U.S. Securities and Exchange Commission, the gasifiers and chemical plant will be scrapped by 2024. Remediation of the Liberty lignite mine will be completed this year.

Bigger Pie Forum Projects

PERS

Legislative Session 2020

Inquiries

Timeline of events surrounding Kemper cost projections – DETAILED

  Click here to see view the Detailed Cost Analysis Timeline for Kemper in detail.

Read More...
Kemper Project clean coal power plant

SEC investigating Southern Company over Kemper Project

The U.S. Securities and Exchange Commission is conducting an investigation of Southern Company and its subsidiary Mississippi Power over costs and delays at the Kemper Project clean coal power plant.

Read More...
The Boundary Dam Power Station in Saskatchewan, owned by SaskPower

Unsealed Kemper Project records could be revealing

“Bill Kelly, a CPA and subcontractor for AECOM who runs the accounting component of the independent monitor team, said the increase amounted to 95 percent of total project cost and amounted to a “material weakness in internal control over financial reporting” You might call this cooking the books.

Read More...
The Kemper combined cycle plant

Lawsuit alleges fraud over ‘goliath’ Kemper Project power plant

Mississippi’s Kemper Project integrated coal gasification power plant hasn’t generated any power off its primary fuel, but it has generated one thing in bunches: lawsuits.

Read More...
Kemper County IGCC Plant

Kemper: An Imprudent Decision, Part 2

Brett Wingo, former Kemper construction supervisor, warned Southern Company executives in 2014 they were reporting false construction timelines for Kemper completion.

Read More...
Trust

Earned mistrust

That may be why people who mistrust government are staunch supporters of freedom of the press and the right of citizens to bear arms.

Read More...